Planning quantities: square metres, waste and container loads
How to turn drawings into an order quantity, why a waste allowance is needed, and why minimum orders follow container loads.
Systems on this site are ordered by quantity of finished surface. Getting that number right avoids two expensive outcomes: running short at the end of the installation, or paying to ship material that is never used.
Step 1: measure the net area
Take the area to be covered from the elevations or ceiling plans and subtract openings such as windows, doors and large service penetrations. This is the net area.
Step 2: add for cutting and waste
Panels are cut at corners, around openings and at the edges of the surface, and offcuts cannot always be reused. Some pieces are damaged in handling. The allowance depends on the design:
- simple, regular surfaces set out to the panel module need the least;
- many openings, corners or small areas need more;
- diagonal layouts, curves and large-format panels need the most.
A small allowance for cutting is already included in the quantities behind each system price. For anything other than a regular surface, add your own margin based on the panel layout, and keep a few spare panels for future repairs, because a later batch may differ slightly in colour.
Step 3: check the minimum order
Each system page shows a minimum order. It corresponds to roughly one 40-foot high-cube container of that system. The reason is cost: sea freight is charged per container, so a full container gives the lowest freight cost per unit, and a balanced full load can be packed and secured properly.
How much fits in a container depends on whether the load is limited by weight or by volume. Dense systems such as stone or ceramic reach the weight limit first; light, bulky systems such as ceiling baffles fill the space first. That is why minimum quantities differ so much from one system to another.
Step 4: think about phasing
- Order each colour or finish in one production batch where possible.
- If the project is built in phases, plan shipments around the installation programme and available storage.
- If you need a quantity below the minimum, contact us before ordering.
If you are unsure about a quantity, contact us before placing the order.
This article is general guidance. Project requirements, local building regulations and the specification confirmed with your order always take priority.
More articles
- Buying a building system instead of separate products Buying Guide
- How a ventilated rainscreen facade works Facade Systems
- Concealed or visible fixing for facade panels Facade Systems